Evaluasi Perhitungan Material Dan Biaya Besi Pada Proyek Rumah Dinas Polres Kota Sukabumi
DOI:
https://doi.org/10.37150/jsts.v2i1.676Keywords:
Iron Reinforced, Bar Bending Schedule, Material, CostingAbstract
Bar Bending Schedule (BBS) has known as calculating for iron reinforced in the projects. BBS is more accurate than calculating manually. This study to evaluate the iron reinforced in material and costing aspects with BBS methode, the case of study is Rumah Dinas Polres Kota Sukabumi project.
The result shower there is gap in calculating for iron using, it is more material about 2513,93 Kg for iron ø13, it will be iron waste in the project. And there are gap in calculating for iron using, there are less for iron material about dia. Ø8 = 46,57 Kg, ø10 = 67,38 Kg. More or less in iron planning will make the project more efficient.